East Campus Fiber Ring / Rec. Center [Facilities Mgmt]

75%

Status

In Progress [In Progress]

75% complete, updated on Wed 10/2/24 12:41 PM by Zackary Potter

Changed Status from Hold-Campus or Vendor Constraints to In Progress.
Changed Health from On Hold to Green - On track.
Mike reports that Fiber has been pulled and now just needs to be terminated.

Details

Dates
Wed 1/1/25 - Mon 6/30/25
Acct/Dept
VP for Administration
Type
Technology Services / IT Project Request
Health
Green - On track
Portfolio(s)
Classification
Projects
Requirements
This is a Facilities Management project
Created
Thu 10/25/18 1:04 PM
Modified
Wed 10/2/24 12:41 PM
Contact Number
Enter primary contact persons phone number. Please use the following format: xxx - xxx - xxxx
278-6635
Requestor Name
Mike Garvey
Division Delegate
Your delegate is your Division's VP or another member of your Division's staff who has the authority to approve this project request. Please select the delegate for your Division.
Bao Johri - Technology Services
If this project is not done, what is the Impact to the University, College, or Department?
Describe in as much detail as possible how this project supports the initiative.
N/A
Is it Mandatory, Regulatory, Compliance, or Accreditation? (Check all that apply)
Please check all that apply.
Not Applicable
Is this a Business Opportunity, Process Improvement, or Value-add? (Check all that apply)
Example: Redefining processes to make them more efficient; Reducing time it takes for a service; Improving cross campus department collaboration.
Value-add
Estimated End Date
10/25/2021

Description

TS to provide secondary route to Save Mart Center / Student Rec Center

Manager

Alternate Manager(s)

Stakeholders (3)

AX
Ar Xiong
Consulted, Informed
Working with this team starting 7/8/19
Fri 7/5/19 8:52 AM
EG
Elizabeth Gonzalez
Consulted, Informed
C/I
Thu 10/8/20 9:47 AM
RG
Robert Guinn
Consulted, Informed
N/A
Fri 11/2/18 3:47 PM